Reed Bed Construction
Photo Gallery

Click on the image to see a larger picture

6 February 2002.

The area where the reed bed was to be constructed was overgrown with trees, shrubs and weeds. As this was mainly a marshland, with two streams flowing through it, a board walk was constructed leading to a viewing platform on the bank of the Welsh Harp Reservoir.

This is a newly repaired boardwalk, replacing a previous old one.

digging begins

13 February 2002.
The overgrown is removed.

the reed bed is getting larger

16 February 2002
The area cleared and digging begins..

You can see the depth

16 February 2002
A channel is dug up to redirect the streams.

extension of reed bed

19 February 2002
The work goes on.

reed bed construction

19 February 2002
The reed bed is getting deeper.

25 February 2002
Digging is finished.

25 February 2002
The reed bed is ready for planting.



May 2002
A viewing platform is constructed

May 2002
Grass begins to grow on the reedbed's banks

May 2002
The first reeds have been planted

 

 